if you assign a resource 25% to a task during several days and the resorces
reports more than 2 hours one day, the % of assignment changes to a grater
value. If this occurs in all project task, it is not possible for the PM to
know the orginal % of assignment and, in fact, with the value that Project
continues re-plannig the task.
¿Is it possible to show this original value for each task?