M
Micheal
Hi,
Case 1:
-------
if the manager assign the task to the user with one day duration and 100%
assignment units . and user complete this task soon with in 3 hours . how he
will mention other 7 hours.
Case 2:
--------
If the manager assign the task to the user with the 2 days duration . but
the user still not complete that task after entering 2 days actual hours in
time sheet and the working of the user in that tasks is continue upto 3rd
days what he will do how he will mention his more hours.
means user is not completed the task in that duration in which he has
assigned.
what is the working of manager and user in EPM if the user is not compeleted
his task within provided duration.
regards
Micheal
Case 1:
-------
if the manager assign the task to the user with one day duration and 100%
assignment units . and user complete this task soon with in 3 hours . how he
will mention other 7 hours.
Case 2:
--------
If the manager assign the task to the user with the 2 days duration . but
the user still not complete that task after entering 2 days actual hours in
time sheet and the working of the user in that tasks is continue upto 3rd
days what he will do how he will mention his more hours.
means user is not completed the task in that duration in which he has
assigned.
what is the working of manager and user in EPM if the user is not compeleted
his task within provided duration.
regards
Micheal