How to move Project server 2007 from VM to Physical Win 2003 Serve

I

Imran Admin

Hi

I have configured and tested a project server 2007 SP1 on VM workstation on
windows server 2003 with shareporint service. now i wants to move the whole
setup and configuration to different physical production server, SQL database
is already on physical separate server only applicaiton server is installed
on VM workstaion for test.... can some one give me step by step info to move
this Project server exactly as it is on VM to new server.

Your help will be highly appriciated.

also if some one can forward me link to find the cost of project server 2007
and project server 2010 for 30 Users.
 
G

Gary Chefetz

Imran:

If the databases are already on the SQL Server that you want them to be on,
then you simply need to install to the new server and connect to the
existing databases rather than creating new ones. Your customizations and
configurations are contained in the database, unless you've done something
out of band on the server.
 