How to move resources with their vacation hours

M

Micheal

Hi,

I need to move two resources from first administrative project to another
with their vacations hours . and I need to fully remove those users from the
first administrative project . and to another administrative with their
previous one year vacations. How I can do this.
Pls reply me soon.

Regards
Micheal
 
R

Rick Roszko

(a) Add the resource name into the second admin project.
(b) Go to the first project, go to the Resource Usage view.
(c) In the right pane, right click on your mouse and choose "Actual Work"
(d) Highlight the data for that user and copy.
(e) Pase the information in the second plan. Save
(f) Once all dats is moved and verified, delete the user in the first plan.
(g) Done.


Go to the first project
 

Ask a Question

Want to reply to this thread or ask your own question?

You'll need to choose a username for the site, which only take a couple of moments. After that, you can post your question and our members will help you out.

Ask a Question

Top