P
pjelliott
Using Project 2007 SP2 I have a project that has a significant number of
tasks, a number of which are dependent on others, and which is currently
scheduled to finish on 04/01/2011.
Following review, I need to move the whole project forward such that the
revised finish date is somewhat earlier on 08/10/2010.
I have tried dragging the final task back in the hope that all preceeding
tasks would go back with it but, of course, Project will not allow this as it
will cause a scheduling conflict.
Is there an easy way that I can pull back the whole project based on the
revised completion date please?
Many thanks
Kind regards
Peter
tasks, a number of which are dependent on others, and which is currently
scheduled to finish on 04/01/2011.
Following review, I need to move the whole project forward such that the
revised finish date is somewhat earlier on 08/10/2010.
I have tried dragging the final task back in the hope that all preceeding
tasks would go back with it but, of course, Project will not allow this as it
will cause a scheduling conflict.
Is there an easy way that I can pull back the whole project based on the
revised completion date please?
Many thanks
Kind regards
Peter