Hello
For Maintenance project, we would like to see the work of a task being
spread along the year for assigned resources.
Parameters used for this kind of task T1: Fixed duration (Duration = 250d) /
No effort driven / Start date=Jan 02 / End date=Dec 29 / Contrainst type=Must
finish on=Dec 29.
So, for Resource R1, if the total work is 12d, we can observe 1d per month.
And for Resource R2, if the total of work si 24d, we can observe 2d per
month.
But, after updating Actuals in the project, the end date of each assignment
changes. The Work contour moves from Flat to Contoured automatically. So,
task T1 for R1 could finish on Sept and for R2 on Oct. That's what we do not
want!
We want the T1 to finish on Dec 29 and the remaining Work spreads equally
during the remaining months of the year.
Any idea of how to?
Many thanks in advance
For Maintenance project, we would like to see the work of a task being
spread along the year for assigned resources.
Parameters used for this kind of task T1: Fixed duration (Duration = 250d) /
No effort driven / Start date=Jan 02 / End date=Dec 29 / Contrainst type=Must
finish on=Dec 29.
So, for Resource R1, if the total work is 12d, we can observe 1d per month.
And for Resource R2, if the total of work si 24d, we can observe 2d per
month.
But, after updating Actuals in the project, the end date of each assignment
changes. The Work contour moves from Flat to Contoured automatically. So,
task T1 for R1 could finish on Sept and for R2 on Oct. That's what we do not
want!
We want the T1 to finish on Dec 29 and the remaining Work spreads equally
during the remaining months of the year.
Any idea of how to?
Many thanks in advance