How to print a daily report of today's tasks?

K

kbutz

I want to print a daily report of today's tasks. I think that I roughly
figured out how to do this. Now the fun part: Some tasks are day shift
tasks, and others are night shift tasks. How do I print out a 'daily'
report, but a separate one for the day shift and for the night shift?
Essentially, I'm looking for a way to have a report of each shift's tasks.
 
S

Steve House [MS Project MVP]

Using the resource usage view and setting up a grouping on base calendar
might do it for you.
 
S

Sarah

How did you set up your report? Is it actually a report, or printed
from a view? Either way, you should be able to set up a filter that
would show day or night shift tasks.

Sarah
kikos@(removethis)nationwide.com
 
K

KellyB

Thanks for the suggestion.

I've set up my report as a Task Report, grouped on 1 Day.
I've changed my Resource Group field to indicate Daytime workers and
Nightime workers, then I filtered using the Resource Group field.

By filtering for either Resource Group = D or = N, I can create a report for
the day shift tasks, or the night shift tasks.

Thanks.
 