How to put text (resource name) in gantt view in PWA

R

Reader Rabbit

Trying to add some text in the project view. Anybody been able to put a
resource or notes field in a gantt view in PWA?

Thanks

Rich
 
M

Marc Soester

Hi Reader Rabbit,

yes you can add notes to a Project View within PWA.
Go to Admin > Manage Views > View Type = Projects
add or modify a particular view.
Search for "Notes" in the "Available fields" and move them over to the
"Displayed fields".
This will ensure that you can view notes in your PWA Project View
Hope this helps
 
R

Reader Rabbit

Marc,

Thanks for the reply.

Perhaps I should have been more explicit. What you suggested is how to add
a column to the view. I want to add text on the gantt chart itself, as in
to the right of the blue bar on a given task. Basicaly I want to have as
few columns listed to maximize the viewable "bars" and still be able to see
the resource or note name. As this is easy in project 2k3, I was hoping
they would have brought this over to the web part.

Any ideas?

Thanks

RMorgan
 

Ask a Question

Want to reply to this thread or ask your own question?

You'll need to choose a username for the site, which only take a couple of moments. After that, you can post your question and our members will help you out.

Ask a Question

Top