I am using Project 2000. I don't know if the example I added below is
helpful but it is a live example. I am trying to understand the Summary
Progress bar under the black Summary bar on my Gantt chart. The Summary bar
says I am 92% complete Summary Progress as of 1/27/05. Start Date 12/26/04
Duration 40 days. I can see that in my data. But why is the Summary Progress
as of 1/27/05 when todays date is 1/12/04. I need to understand more fully
the Summary Progress function within the black Summary bar. Thanks
SPANDEX R&D (SWEDEN) 36.67d 40d? Mon
12/6/04 Fri 1/28/05 92% 3.33d? NA NA
Documentation & Evaluation 11d 11d? Mon
12/6/04 Mon 12/20/04 100% 0d? NA Mon 12/20/04
Initial Testing
11d 11d? Mon 12/6/04 Mon 12/20/04 100% 0d? NA Mon 12/20/04
Review Corrective Action Plans With Management 0d 2d? Thu 1/27/05 Fri
1/28/05 0% 2d? NA NA
helpful but it is a live example. I am trying to understand the Summary
Progress bar under the black Summary bar on my Gantt chart. The Summary bar
says I am 92% complete Summary Progress as of 1/27/05. Start Date 12/26/04
Duration 40 days. I can see that in my data. But why is the Summary Progress
as of 1/27/05 when todays date is 1/12/04. I need to understand more fully
the Summary Progress function within the black Summary bar. Thanks
SPANDEX R&D (SWEDEN) 36.67d 40d? Mon
12/6/04 Fri 1/28/05 92% 3.33d? NA NA
Documentation & Evaluation 11d 11d? Mon
12/6/04 Mon 12/20/04 100% 0d? NA Mon 12/20/04
Initial Testing
11d 11d? Mon 12/6/04 Mon 12/20/04 100% 0d? NA Mon 12/20/04
Review Corrective Action Plans With Management 0d 2d? Thu 1/27/05 Fri
1/28/05 0% 2d? NA NA