How to rebaseline ONLY costs (new rates for people) in project?

D

Dawn

After you update the rates in the resource sheet with an effective date, is
there a way for you to get the new costs into the baseline cost? I don't
want to have to rebaseline my entire plan, or even part of it, and have the
baseline the dates. I only want to baseline the costs. Any way to do that???
 
J

John

Dawn said:
After you update the rates in the resource sheet with an effective date, is
there a way for you to get the new costs into the baseline cost? I don't
want to have to rebaseline my entire plan, or even part of it, and have the
baseline the dates. I only want to baseline the costs. Any way to do that???

Dawn,
Well, baseline is baseline, when a whole project or selected tasks from
a project are baselined ALL baseline fields are updated. But, with
Project 2003, (it may also be true for 2002), multiple baselines can be
set. Go to Tools/Tracking/Save Baseline and select one of the 10 other
baselines.

John
Project MVP
 