M
Mike R
Previously, I created my project tasks, days required, dependenies etc
and MS-project calculated the end-phase-one milestone to be after 4
weeks.
Two weeks later, I have input remaining-days information for all the
tasks and I expected that MS-project would then automatically
recalculate the end-date milestone to be a further 3 weeks after the
original estimate, ie showing slippage.
But it didn't. It seems that MS-project only (re)calculates based on
work values.
How can I have MS-project derive the new end-date from remaining-days
data?
and MS-project calculated the end-phase-one milestone to be after 4
weeks.
Two weeks later, I have input remaining-days information for all the
tasks and I expected that MS-project would then automatically
recalculate the end-date milestone to be a further 3 weeks after the
original estimate, ie showing slippage.
But it didn't. It seems that MS-project only (re)calculates based on
work values.
How can I have MS-project derive the new end-date from remaining-days
data?