J
Jack Dahlgren MVP
Hit the F9 key and see what happens.
-Jack Dahlgren
-Jack Dahlgren
SProvost said:Thank you to all for your answers. It is reassuring that leveling will
resolve overallocations that are the results of the resource being
assigned
to concurrent tasks. This is what I am trying to solve.
Obviously the project has a start date. I marked all tasks to start as
soon
as possible. I assigned resources to all tasks. Calculation is set to
automatic. Priority of tasks is set to 500. That seems to be the default.
Does it need to be set to 1000?
The only leveling options on are: Leveling can adjust individual assign...
and the split work option.
Again, I really appreciate your help .
I am not sure what this means: Aren't resources assigned to units higher
than their max units?
Steve House said:Adding a note to Jack's comments, in addition to the points he made,
leveling resolves overallocations that are the result of a resource being
assigned to 2 or more concurrent tasks resulting in a total allocation
that
exceeds his maximum. If he's assigned to a SINGLE task at more than his
maximum allocation leveling cannot fix it. This commonly occurs when Joe
has been assigned to tasks at 100% and then you find out he's only
available
a max of, say, 50%. Updating his Maximum Allocation field on the
Resource
Sheet to the new maximum does not ripple over to automatically change his
assignment level on tasks he's already been assigned to, instead merely
showing him as overallocated on them. He's assigned to Wax Widgets at
100%
but is only available a max of 50% - that sort of over must be resolved
manually on a task-by-task basis, leveling won't touch it.
--
Steve House [Project MVP]
MS Project Trainer & Consultant
Visit http://project.mvps.org/faqs.htm for the FAQs
SProvost said:Wow, there are so many things to check. Do you mean that leveling will
work
ONLY if I assign resources to all tasks AND I make sure all tasks have
actual
start dates AND I set calculation to automatic AND resources are not
assigned
to units higher than their maximum units AND task priority is NOT 1000
AND
the leveling option "Level only within available slack" is NOT on?
Did I get every one of these right? Or did I understand just the
opposite
of
what you meant, for some of these?
:
Hi,
There are so many ways to make leveling not work that this is
guesswork.
Did you asisgn resources to all tasks?
Don't tasks have actual start dates?
Isn't calculation set to manual (that is the F9 trick to test)?
Aren't resources assigned to units higher than their max units?
Is priority of the tasks set to 1000?
Don't you have the leveling option "Level only within available slack"
on?
Maybe I forget some..
--
Jan De Messemaeker
Microsoft Project Most Valuable Professional
+32 495 300 620
For availability check:
http://users.online.be/prom-ade/Calendar.pdf
I want to level my project but nothing happens.
A theory says it is because of contraints. I slected all tasks and
set
them
to as soon as possible.
It still does not work.
How can I level, so I can see when the project really ends?
Steve House said:Adding a note to Jack's comments, in addition to the points he made,
leveling resolves overallocations that are the result of a resource being
assigned to 2 or more concurrent tasks resulting in a total allocation that
exceeds his maximum. If he's assigned to a SINGLE task at more than his
maximum allocation leveling cannot fix it. This commonly occurs when Joe
has been assigned to tasks at 100% and then you find out he's only available
a max of, say, 50%. Updating his Maximum Allocation field on the Resource
Sheet to the new maximum does not ripple over to automatically change his
assignment level on tasks he's already been assigned to, instead merely
showing him as overallocated on them. He's assigned to Wax Widgets at 100%
but is only available a max of 50% - that sort of over must be resolved
manually on a task-by-task basis, leveling won't touch it.
--
Steve House [Project MVP]
MS Project Trainer & Consultant
Visit http://project.mvps.org/faqs.htm for the FAQs
SProvost said:Wow, there are so many things to check. Do you mean that leveling will
work
ONLY if I assign resources to all tasks AND I make sure all tasks have
actual
start dates AND I set calculation to automatic AND resources are not
assigned
to units higher than their maximum units AND task priority is NOT 1000 AND
the leveling option "Level only within available slack" is NOT on?
Did I get every one of these right? Or did I understand just the opposite
of
what you meant, for some of these?
SProvost said:Thank you to all for your answers. It is reassuring that leveling will
resolve overallocations that are the results of the resource being
assigned
to concurrent tasks. This is what I am trying to solve.
Obviously the project has a start date. I marked all tasks to start as
soon
as possible. I assigned resources to all tasks. Calculation is set to
automatic. Priority of tasks is set to 500. That seems to be the default.
Does it need to be set to 1000?
The only leveling options on are: Leveling can adjust individual assign...
and the split work option.
Again, I really appreciate your help .
I am not sure what this means: Aren't resources assigned to units higher
than their max units?
Steve House said:Adding a note to Jack's comments, in addition to the points he made,
leveling resolves overallocations that are the result of a resource being
assigned to 2 or more concurrent tasks resulting in a total allocation
that
exceeds his maximum. If he's assigned to a SINGLE task at more than his
maximum allocation leveling cannot fix it. This commonly occurs when Joe
has been assigned to tasks at 100% and then you find out he's only
available
a max of, say, 50%. Updating his Maximum Allocation field on the
Resource
Sheet to the new maximum does not ripple over to automatically change his
assignment level on tasks he's already been assigned to, instead merely
showing him as overallocated on them. He's assigned to Wax Widgets at
100%
but is only available a max of 50% - that sort of over must be resolved
manually on a task-by-task basis, leveling won't touch it.
--
Steve House [Project MVP]
MS Project Trainer & Consultant
Visit http://project.mvps.org/faqs.htm for the FAQs
SProvost said:Wow, there are so many things to check. Do you mean that leveling will
work
ONLY if I assign resources to all tasks AND I make sure all tasks have
actual
start dates AND I set calculation to automatic AND resources are not
assigned
to units higher than their maximum units AND task priority is NOT 1000
AND
the leveling option "Level only within available slack" is NOT on?
Did I get every one of these right? Or did I understand just the
opposite
of
what you meant, for some of these?
:
Hi,
There are so many ways to make leveling not work that this is
guesswork.
Did you asisgn resources to all tasks?
Don't tasks have actual start dates?
Isn't calculation set to manual (that is the F9 trick to test)?
Aren't resources assigned to units higher than their max units?
Is priority of the tasks set to 1000?
Don't you have the leveling option "Level only within available slack"
on?
Maybe I forget some..
--
Jan De Messemaeker
Microsoft Project Most Valuable Professional
+32 495 300 620
For availability check:
http://users.online.be/prom-ade/Calendar.pdf
I want to level my project but nothing happens.
A theory says it is because of contraints. I slected all tasks and
set
them
to as soon as possible.
It still does not work.
How can I level, so I can see when the project really ends?
Want to reply to this thread or ask your own question?
You'll need to choose a username for the site, which only take a couple of moments. After that, you can post your question and our members will help you out.