Some of my project resources complaining that they can see multiple copies of
the same tasks with different dates. Only one of them is correct. They are
asking me to remove duplicate incorrect tasks assignemnts from their view.
It might have happened when the database went out of sync due to recent
changes I made in the project redistributing some of the tasks to new
resources and the project server failed to remove the tasks already published
from those resources who are not assigned any more. How can I remove those
duplicates task assignments?
the same tasks with different dates. Only one of them is correct. They are
asking me to remove duplicate incorrect tasks assignemnts from their view.
It might have happened when the database went out of sync due to recent
changes I made in the project redistributing some of the tasks to new
resources and the project server failed to remove the tasks already published
from those resources who are not assigned any more. How can I remove those
duplicates task assignments?