Hello –
I see an “Unassigned Resource†in the Data Analysis view with $$cost
,however when I check my project plan I find a local resource called
"unassigned" but there is no work or cost against that resource.
Can anyone explain how can I get rid of the dollars assigned to the
unassigned resource?
PS: There are some other resources in the team that are added to a task but
their % allocation and cost is zero(0).