C
crizco
I can't seem to find a way to replace a portion of multiple generics with a
named resource. For example, I assign a generic resource at 200% to a task.
Say later on, only one needs to be replace by a named resource which should
still leave one generic. So orignally I had Generic = 200%, then replaced one
so it should now be Generic = 100% and John Doe = 100%. When I do a replace,
I get all the work transferred to the named resource. Is there a way to split
that up? Thanks!
(Running Project Server 2003.)
named resource. For example, I assign a generic resource at 200% to a task.
Say later on, only one needs to be replace by a named resource which should
still leave one generic. So orignally I had Generic = 200%, then replaced one
so it should now be Generic = 100% and John Doe = 100%. When I do a replace,
I get all the work transferred to the named resource. Is there a way to split
that up? Thanks!
(Running Project Server 2003.)