How to replace in resource in the future

X

Xiao

Hello,
Project Server 2007
What could be the best practice to schedule the replacement of the resource
assigned to a task, with another one, but in the future, not right now?
Thanks
 
D

Dale Howard [MVP]

Xiao --

There is no way to schedule future resource assignments. It must simply be
done manually when that future date arrives. Hope this helps.
 
S

Sean Hanson

I agree with Dale, what you want is not the way the tool works necessarily.
My thought would be to set the current resource to complete work at the
assignment level by a date in the future. Then add the replacement resource
for the future work, setting a scheduling delay on them to begin after the
original resource completes their work.
--
Sean Hanson

http://www.randsmanagement.com
Mass Resource Tool for 2007
Project Server 2007 Archive Tool
2007 ULS Log Reporting
SRS Report Packs
 

Ask a Question

Want to reply to this thread or ask your own question?

You'll need to choose a username for the site, which only take a couple of moments. After that, you can post your question and our members will help you out.

Ask a Question

Top