It works, but I consider it as a bad practice.
In 2003 (and I'm not sure about 2007), if you drag an assignment without actual work to a new resource, the UID is also transferred, while a new assignment UID should have been created. This can be important in case you have reports or customizations that rely on the assignment UID.
So I prefer the method Jan has described, rather than using drag and drop.
Projectopolis
Andrew Lavinsky wrote: Sure it works. Here's how to recreate it:
1) In the Resource Sheet, create two resources: Bob and Sam
2) Create one task, make it a duration of 10d, assign it to Bob.
3) Set it to 50% complete.
4) In the Resource Usage View, grab the task under Bob, and you can drag it under Sam.
Perhaps this functionality has been disabled in the Belgian release.....?
-A
Hi Andrew,
Are you sure? I've never seen this and can't make it work.
I do it by showing the Assign Resources Form, click the resoruce,
replace,
the new resource, OK.
That indeed replaces remaining work but not actual work.
Hope this helps,