how to require resources to work on assignment at same time?

N

ngs1

Hi, how can I specify to project 2003 that for a particular task I want the
resources to work together at the same time - and therefore schedule the
first available date that suits all resources (instead of splitting the work.)
 
J

Jan De Messemaeker

Hi,

One of my major frustrations.. not possible without doing Resource leveling
(there is an article on this on my website - showing non working time as
tasks)
 
N

ngs1

Quite an oversight on the part of the software authors .... to run into a
problem like this after using the software for less than a week is not
encouraging.

I'll look into your method, thanks for your help.
 
J

JulieD

Hi Jan

this is probably my major frustration with project too .. do you think that
it will ever be introduced as an option? (i've wishlisted it a couple of
times!)

Cheers
JulieD
 
J

Jan De Messemaeker

Who knows? I'we listed and supported it as much as I could..

"When a pilot is on holiday, the plane does the flying by itself and the
pilot performs his part of the work when he comes back"
 
J

JulieD

Hi Jan

we live i hope :)

my (true life) examples are a crane & crane driver managing to do their work
quite separately ... and a meeting schedule for one of the participants at
3am and the other at 9am :)

Cheers
JulieD
 