We are using Project Pro and Server 2003, and have published several normal
projects and one admin project. Question:
How can a resource submit a timesheet with zero actual work. In other
words, this resource has no hours to charge to any published projects, not
even to the admin project. It seems like each resource has to charge hours
to at least one of the projects in order to get rid of the "Unsubmitted
timesheets" warning (without disabling timesheet approval process). Is there
a way around this?
I appreaciate your attention.
-Eren
projects and one admin project. Question:
How can a resource submit a timesheet with zero actual work. In other
words, this resource has no hours to charge to any published projects, not
even to the admin project. It seems like each resource has to charge hours
to at least one of the projects in order to get rid of the "Unsubmitted
timesheets" warning (without disabling timesheet approval process). Is there
a way around this?
I appreaciate your attention.