How to retrieve AssignmentBaseline0Work information?

J

jpa

Hi
(PS2007, SP1, PIU)
I wrote a Reporting Service report able to display, for a given resource,
for each task, Assignment Work on a per day per day basis.
I got above information from database within
MSP_EpmAssignmentByDay.AssignmentWork.
Actual Work is retrieved thru MSP_EpmAssignmentByDay.AssignmentActualWork.
I 'd like to compare Actual Work with baseline assignment...
My project are baselined.
At the time being I cannot find information of Baseline Work:
MSP_EpmAssignmentByDay_UserView.AssignmentBaseline0Work is NULL.

Why this information is not set? Any reason?
Is there any specific setting to care about when setting the baseline?
Thanks in advance
jpa
 
J

jpa

Hi again,
When investigating deeper about my issue I found next patch (from March 6th,
2009): http://support.microsoft.com/kb/968271/en-us
Maybe that what I see is an already referenced issue... In my case I don't
use (directly) the PSI. Work is updated from Timesheet filling.
Can somebody confirm this patch will solve my problem?
Thank again for your support
jpa
 