Hi
(PS2007, SP1, PIU)
I wrote a Reporting Service report able to display, for a given resource,
for each task, Assignment Work on a per day per day basis.
I got above information from database within
MSP_EpmAssignmentByDay.AssignmentWork.
Actual Work is retrieved thru MSP_EpmAssignmentByDay.AssignmentActualWork.
I 'd like to compare Actual Work with baseline assignment...
My project are baselined.
At the time being I cannot find information of Baseline Work:
MSP_EpmAssignmentByDay_UserView.AssignmentBaseline0Work is NULL.
Why this information is not set? Any reason?
Is there any specific setting to care about when setting the baseline?
Thanks in advance
jpa
(PS2007, SP1, PIU)
I wrote a Reporting Service report able to display, for a given resource,
for each task, Assignment Work on a per day per day basis.
I got above information from database within
MSP_EpmAssignmentByDay.AssignmentWork.
Actual Work is retrieved thru MSP_EpmAssignmentByDay.AssignmentActualWork.
I 'd like to compare Actual Work with baseline assignment...
My project are baselined.
At the time being I cannot find information of Baseline Work:
MSP_EpmAssignmentByDay_UserView.AssignmentBaseline0Work is NULL.
Why this information is not set? Any reason?
Is there any specific setting to care about when setting the baseline?
Thanks in advance
jpa