How to Revmove Completed Tasks when showing 100% in PWA?

S

spatton

In PWA, a user will complete a task and submit as 100%, however, this
still shows in their view (as 100%) but also as a task. Why does this
remain, even if at 100%? Is there a way the PWA user can remove a task
once it reaches 100%?

We are using MS Project 2007 Server SR1

Thanks

Steve
 
D

Dale Howard [MVP]

Steve --

If the user has selected the "Show only current task" option in the View
Options pane on the My Tasks page, then the completed task will disappear in
10 days, or in the number of days defined by the Project Server
administrator as a Current task. Hope this helps.
 
R

radman57

In PWA, a user will complete a task and submit as 100%, however, this
still shows in their view (as 100%) but also as a task.  Why does this
remain, even if at 100%? Is there a way the PWA user can remove a task
once it reaches 100%?

We are using MS Project 2007 Server SR1

Thanks

Steve

Steve:

If you are talking about the My tasks view for an individual team
member, the default definition of tasks that appear in that view (i.e.
current tasks) is current date +/- 10 days. You would need to change
the definition of "current tasks" in order for the completed tasks to
disappear before 10 days. If they are remaining longer than 10 days,
check with your administrator for the definition of "current tasks" as
defined for your enterprise. I hope this helps
 