how to schedule a task to start on the next full working day

  • Thread starter Steve Douglas P2p, MCP
  • Start date
S

Steve Douglas P2p, MCP

Hi All,

Does anyone know how to set a task to always start on the next full
day?

ie, if task a starts on monday morning, with a 2.5 day duration, i
want task b to start on the next full day ie. Wednesday. if task a
overan to 3.7 days I would want task b to start on Thursday.

Many Thanks
 
J

Jim Aksel

Answered with your first post -- "Start task at beginning of next day" (5
posts earlier than this one)
--
If this post was helpful, please consider rating it.

Jim
It''s software; it''s not allowed to win.

Visit http://project.mvps.org/ for FAQs and more information
about Microsoft Project
 
S

Steve House

Please clarify ... if a task starting Monday takes 2.5 days, it finishes
mid-day on Wednesday and the next full day begins Thursday morning, not
Wednesday as you suggest in your example. And 3.7 days would have the next
task begin Friday, not Thursday, if it has to start at the start of the
workday.
 