G
Gil
Hi all,
We are using Project Server 2007. Resources submit actual work daily,
no timesheet.
I want to be able to check once a week how much actual work resources
have submitted last week.
As I understand, the data in PWA (Resource assignments view or Data
analysis) will be updated only after all project managers accept all
updates, and publish all projects.
The problem is that until I get that done, the report is irrelevant…
As an administrator, I can publish the projects myself, but this does
not solve the "accept updates by project managers first" problem.
What are my options? Can I get the data from somewhere else, right
after resources have saved it to the server, even if it is not
accepted and published yet?
Thanks, Gil
We are using Project Server 2007. Resources submit actual work daily,
no timesheet.
I want to be able to check once a week how much actual work resources
have submitted last week.
As I understand, the data in PWA (Resource assignments view or Data
analysis) will be updated only after all project managers accept all
updates, and publish all projects.
The problem is that until I get that done, the report is irrelevant…
As an administrator, I can publish the projects myself, but this does
not solve the "accept updates by project managers first" problem.
What are my options? Can I get the data from somewhere else, right
after resources have saved it to the server, even if it is not
accepted and published yet?
Thanks, Gil