How to see and input hours worked int tasks onwed by other resourc

M

MarcosLima

Gentlemen

I'm working with Project Server 2003 and have an Enterprise project
published with some resources besides me. I'm the administrator and manager
of this project.

How can I see in Project Web Access tasks allocated to another resources?

And else how can I input worked hours in those tasks?

Thanks
Marcos
 
D

Dale Howard [MVP]

Marcos --

Assuming you have permission to view other resources, here are the answers:

1. In PWA, click Resources - View Resource Assignments.

2. Ask your Project Server administrator to enable the Adjust Actuals
permission in the Permissions grid and the View Adjust Actual permission in
the Global Permissions grid of the Project Managers group. You can then use
Resources - Adjust Actuals to enter actuals for those other resources.

Hope this helps.
 