How to see how long a group of tasks will take to complete

B

brinkster11

We are using MS Project Server 2007.

I have 20 tasks grouped together.

They can all start on the same day. There are no dependancies. I have
entered the estimate in hours for each item.

I have 2 resources to each item.
Each task is currently set to Fixed Work.
The effort of work on each task is split between the developers.

How do I configure the tasks so project will give me an accurate completion
date. It needs to take into consideration the developers vacation that is
configured as admin time.
 
B

brinkster11

The task all have the same predecessor, several taks have the same successor.

If I link them together one right after the other, the right tasks won't
display on the developers time sheet.
 

Ask a Question

Want to reply to this thread or ask your own question?

You'll need to choose a username for the site, which only take a couple of moments. After that, you can post your question and our members will help you out.

Ask a Question

Top