brinkster11
We are using MS Project Server 2007.
I have 20 tasks grouped together.
They can all start on the same day. There are no dependancies. I have
entered the estimate in hours for each item.
I have 2 resources to each item.
Each task is currently set to Fixed Work.
The effort of work on each task is split between the developers.
How do I configure the tasks so project will give me an accurate completion
date. It needs to take into consideration the developers vacation that is
configured as admin time.
I have 20 tasks grouped together.
They can all start on the same day. There are no dependancies. I have
entered the estimate in hours for each item.
I have 2 resources to each item.
Each task is currently set to Fixed Work.
The effort of work on each task is split between the developers.
How do I configure the tasks so project will give me an accurate completion
date. It needs to take into consideration the developers vacation that is
configured as admin time.