K
karishma
hi
I have been using MSP 2003. in project i have added a % Complete Column. now
i want to add a Text 1 column and in that it should show "Complete" for 100%
Complete", "Not Started for 0% Complete" and "Incomplete for % Complete>0 and
< 100".
I have tried to make formula for that, but it is not working. must be
something wrong with the formula. please suggest me the correct way to get it.
Thanx in advance!!
I have been using MSP 2003. in project i have added a % Complete Column. now
i want to add a Text 1 column and in that it should show "Complete" for 100%
Complete", "Not Started for 0% Complete" and "Incomplete for % Complete>0 and
< 100".
I have tried to make formula for that, but it is not working. must be
something wrong with the formula. please suggest me the correct way to get it.
Thanx in advance!!