J
John Sitka
....not like 12:00AM to 11:59PM cause then it throws .98 hours in Resource
view.
I would like true whole hours.
view.
I would like true whole hours.
Dale Howard said:John --
The 24 hours working calendar that ships with Microsoft Project shows the
time as 12:00 AM to 12:00 AM. Can't you use this calendar as the Base
Calendar for the resource?
And the rules are simple: taks without resources nor task calendar are
scheduled as per the project calendar (but there is this matter of the
default start as long as they aren't linke or anything)
Assignments are scheduled as per the resource calendar but taking into
account the task calendar.
Want to reply to this thread or ask your own question?
You'll need to choose a username for the site, which only take a couple of moments. After that, you can post your question and our members will help you out.