M
Mark Keller
when working with Project Server 2007 I have resources that are working multiple projects at the same time.
On a per project basis I want to define that a resource is working on Project A 60% of the time and Project B 40% of the time.
Since the Max. Units defined on the Resource Sheet reflects what the resource is set to on the server and cannot be changed at the project level, what is the easiest way to define allocations on a per project basis?
Submitted via EggHeadCafe - Software Developer Portal of Choice
BASICS: Make any Method Call "Timeout"-able
http://www.eggheadcafe.com/tutorial...e5-5b61f049019f/basics-make-any-method-c.aspx
On a per project basis I want to define that a resource is working on Project A 60% of the time and Project B 40% of the time.
Since the Max. Units defined on the Resource Sheet reflects what the resource is set to on the server and cannot be changed at the project level, what is the easiest way to define allocations on a per project basis?
Submitted via EggHeadCafe - Software Developer Portal of Choice
BASICS: Make any Method Call "Timeout"-able
http://www.eggheadcafe.com/tutorial...e5-5b61f049019f/basics-make-any-method-c.aspx