C
Craig
Win XP/MS Project 2003
I have a question: How do you make a task start on the next Wednesday after
the predecessor ends? We have a project where we need to have certain tasks
start only on wednesdays or fridays and thus we would like a way to set the
start times to be on the next working Wednesday or next working Friday. Such
a setting would then automatically update during modifications to the overall
Project plan.
Right now we have to manually update each start date everytime we make
changes which of course defeats the purpose of using Project somewhat.
Thanks.
Craig
I have a question: How do you make a task start on the next Wednesday after
the predecessor ends? We have a project where we need to have certain tasks
start only on wednesdays or fridays and thus we would like a way to set the
start times to be on the next working Wednesday or next working Friday. Such
a setting would then automatically update during modifications to the overall
Project plan.
Right now we have to manually update each start date everytime we make
changes which of course defeats the purpose of using Project somewhat.
Thanks.
Craig