How to set default duration to milestone in Microsoft Project?

D

David

How do I set the default duration to "0d" (as in milestone) instead of "1d?"
in Micrsoft Project 2007? I used Project to keep track of only milestones and
it is very cumberstone to click on each task to manually change the duration
to show 0d.

Please help.
 
M

Mike Glen

Hi David,

Welcome to this Microsoft Project newsgroup :)

No, it can't be changed. However, if you select all tasks (the button above
the ID column) then go to Tools/Task Information and enter a zero in the
Duration cell, then OK will set all tssks to zero Duraton. This is a
standard way to insert the same data into a selection of tasks.

FAQs, companion products and other useful Project information can be seen at
this web address: http://project.mvps.org/faqs.htm

Hope this helps - please let us know how you get on :)

Mike Glen
MS Project MVP
See http://tinyurl.com/2xbhc for Project Tutorials
 