How to set duration in days ?

Z

zipzip

My MS-Project 2003 is set in minutes.
I'd like to set duration in days.
How can I do this ?
Thank's
Renê
 
J

Jan De Messemaeker

1. Tools, Macro, Macros, Format_Duration, Run
2. Tools, Options, schedule, Duration is entered in...
HTH
 
R

Renê

Can I set it FOREVER ?
Or need I set it time that I enter to MS-Project ?
Thank's
Renê
 
J

Jan De Messemaeker

Hi Renê

Haven't you noticed the Set As Default button when you set it?
That is the one.
That will set it for all new projects.
For existing projects you will have to reset it.
 
Z

zipzip

No, I haven't. My version is MS-Project 2003 std.
Could you tell me where it is ?
Thank's
Renê
 
J

Jan De Messemaeker

Hi

Under Tools, Options, Schedule there definitely (in all versions I heve ever
seen) is a button "Set as Default" or the equivalent.
HTH
 

Ask a Question

Want to reply to this thread or ask your own question?

You'll need to choose a username for the site, which only take a couple of moments. After that, you can post your question and our members will help you out.

Ask a Question

Top