Hi,
If any of my resources compelet task and set 100% after schedule finish
date, how can i make my "Finish" date equals to Actual Finish date and
update Actual Work automatically which show total hrs spent on a task. My
task calculation settings are automatic and all the four options are
selected
1. Move end of completed parts after status date back to status date
And Move start of remaining parts back to status date
2. Move start of remaining parts before status date forward to status date
And move end of completed parts forward to status date.
My status date is equal to surrent date. Secondly which baseline should i
set in "Earned Value" option, i have set 4 basleline in my project should i
use most recent one.
Thanks
Ayesha
If any of my resources compelet task and set 100% after schedule finish
date, how can i make my "Finish" date equals to Actual Finish date and
update Actual Work automatically which show total hrs spent on a task. My
task calculation settings are automatic and all the four options are
selected
1. Move end of completed parts after status date back to status date
And Move start of remaining parts back to status date
2. Move start of remaining parts before status date forward to status date
And move end of completed parts forward to status date.
My status date is equal to surrent date. Secondly which baseline should i
set in "Earned Value" option, i have set 4 basleline in my project should i
use most recent one.
Thanks
Ayesha