H
Help
I have a macro that updates the project at close. There
are 150 users that are using Project Pro 2002 SP1. During
SP1 upgrade, the Macro security got reset to "High". Is
there a way that the Macro security can be set to Medium
for all the users automatically. Setting it to low on
Enterprise gobal does not seem to work because it is
probably a local setting.
Also, is there a VBA method/procedure that run the Macro
automatically without opening or closing each plan. i.e.
Macro updates all the project plans in Project Server
without opening them in Project Pro.
Please advise.
Thanks!
are 150 users that are using Project Pro 2002 SP1. During
SP1 upgrade, the Macro security got reset to "High". Is
there a way that the Macro security can be set to Medium
for all the users automatically. Setting it to low on
Enterprise gobal does not seem to work because it is
probably a local setting.
Also, is there a VBA method/procedure that run the Macro
automatically without opening or closing each plan. i.e.
Macro updates all the project plans in Project Server
without opening them in Project Pro.
Please advise.
Thanks!