L
Lorveney
Hi,
I am just completing an Access database enhancement to export milestones to
Microsoft project (using office automation in VBA).
Whilst some of these milestones in Access have Baseline and Actual dates,
others are blank. When these 'blamk' milestones are imported into Project
they are given a default date. Is there a way (by setting
Application/Project defaults, perhaps?) of keeping these milestone dates
blank or making them NA or similar?
I am setting the tasks' duration to 0 to make them milestones.
I am using Access 2003 and Project 2007.
Thanks
I am just completing an Access database enhancement to export milestones to
Microsoft project (using office automation in VBA).
Whilst some of these milestones in Access have Baseline and Actual dates,
others are blank. When these 'blamk' milestones are imported into Project
they are given a default date. Is there a way (by setting
Application/Project defaults, perhaps?) of keeping these milestone dates
blank or making them NA or similar?
I am setting the tasks' duration to 0 to make them milestones.
I am using Access 2003 and Project 2007.
Thanks