how to show non working times on the gantt chart

J

Jason

hello,
I was wondering if it is possible to show the non working times on the task
bars as a shaded color, split or something that makes it obvious.

Thank you
 
J

José Miguel Piñeres

Hello Jason,

Welcome to this Microsoft Project General Questions newsgroup.

By default, nonworking hours are shaded in gray color with a dotted pattern
in the Gantt chart’s background.

If you want to make it more obvious, just format the Timescale of the Gantt
chart (double click on it), in the "Non-working time" tab, select a more
vivid color, maybe red. You can also select the option to show nonworking
time “in front of task barsâ€.

I hope this helps. Please let us know how you get along with it.

Best Regards,
 
R

Rod Gill

Also under non-working time you can select a different calendar. Note also
that if you show time on a week by week basis, Weekend non-work doesn't
appear but a whole week off will.

--

Rod Gill
Microsoft MVP for Project

Author of the only book on Project VBA, see:
http://www.projectvbabook.com
 