Hi,
I use MSP server 2003 and MS Project Pro 2003.
On schedule, I have a some task as below:
1. Design
2. Program 1
3. Program 2
4. Coding
5. Program 1
6. Program 2
When user input actual value (Design Program 1, coding program 2) on PWA and
send to leader for approve, the information in Update tab as below:
Program 1.
Program 2.
Leader cannot know Program 1 is design or coding, etc.
How to show summary task in Update tab or another way to solve this problem?
Thanks