J
ja202141
I used the "Reschedule uncompleted work to start after" option in
Tools>Tracking>Update Project. This option has created some split tasks as
it should. I see that the elapsed time between the split tasks is included
in the rolledup duration for that particular phase. Is there anyway to avoid
including the elapsed time. Please note that no elapsed durations are
specified in my project.
Thank you,
Tools>Tracking>Update Project. This option has created some split tasks as
it should. I see that the elapsed time between the split tasks is included
in the rolledup duration for that particular phase. Is there anyway to avoid
including the elapsed time. Please note that no elapsed durations are
specified in my project.
Thank you,