P
peteseats
We have a limited amount of resources in our team and we have wor
piling up. We only have 2 designers and 4 developers, each with ther
own speciality.
We currently have 12 projects that need to be started, but before the
start our lead designer must complete a task (which takes 1 day). Fro
here the devs can start.
How can I get the next task to start only when the RESOURCE i
available, rather than when the task is completed?
The only way I seem to be able to do it is to have a task called th
dev/designer. For instance:
-Project HSBC
-Design
-George Task
-George- (resource)
any ideas?
Thank
piling up. We only have 2 designers and 4 developers, each with ther
own speciality.
We currently have 12 projects that need to be started, but before the
start our lead designer must complete a task (which takes 1 day). Fro
here the devs can start.
How can I get the next task to start only when the RESOURCE i
available, rather than when the task is completed?
The only way I seem to be able to do it is to have a task called th
dev/designer. For instance:
-Project HSBC
-Design
-George Task
-George- (resource)
any ideas?
Thank