How to sychronize the deliverables and the tasks

G

GG

Hi:
I got a question. I created some deliverables in my plan by Project
Professinoal 2007 and link them to some tasks in the plan. After I change the
plan, I realize that the deliverables starting and finishing dates are not
changed accordingly. And i cannot find a way to change them to conform the
plan except manually. Does anyone know if there is a way to synchronize the
deliverables and the linked tasks automatically?

Thanks
Rock
 
D

Dale Howard [MVP]

Rock --

Your assumption is NOT how Project Server 2007 handles Deliverable dates.
Microsoft's assumption about Deliverables is that if your project slips and
you miss a Deliverable date, you must go back to your
client/sponsor/customer and renegotiate a new Deliverable date. And then
you must manually enter the new Deliverable date for the task. Hope this
helps.
 