R
Rabbit
Hi All,
Team members update the actual working hours on timesheet through PWA, but
PM also can update the actual working hours on .mpp file, in this case,
there are data consistency issues between .mpp and timesheet, how does PM
synchronize data once PM opens .mpp file from project server?
Here are the case:
1. PM changes actual working hours on .MPP
2. Save and publish it WITHOUT checking "overwrite actuals in the resource's
timesheet""
3. Team members update timesheet on PWA
4. The data in .mpp file may not be consistent with timesheet when PM opens
..mpp now.
Does project server have any mechanism to avoid this data consistent issue?
Such as prompting warning message, or automatically synchronize data when
opening .mpp from project server.
Thanks in advance,
Rabbit
Team members update the actual working hours on timesheet through PWA, but
PM also can update the actual working hours on .mpp file, in this case,
there are data consistency issues between .mpp and timesheet, how does PM
synchronize data once PM opens .mpp file from project server?
Here are the case:
1. PM changes actual working hours on .MPP
2. Save and publish it WITHOUT checking "overwrite actuals in the resource's
timesheet""
3. Team members update timesheet on PWA
4. The data in .mpp file may not be consistent with timesheet when PM opens
..mpp now.
Does project server have any mechanism to avoid this data consistent issue?
Such as prompting warning message, or automatically synchronize data when
opening .mpp from project server.
Thanks in advance,
Rabbit