N
Na Tanya
I’m new to Project and I thought that someone here might help me with a
question. I am trying to track how long all of my tasks take, i.e. 30
minutes, not 1 day. Ultimately, I want to assign it to a week or a 2-day
window when I will do the task. What keeps happening is that I set the
duration for 30 minutes, but when I put a start and end date then it adds 2
days to my 30 minute task. Case in point, a task would be a 30-minute phone
call but I’m not sure when I can actually make the call but I know it will
happen somewhere on Tuesday or Wednesday. So the duration will and should be
30 minutes, BUT I don’t want the start and finish time to be 3/13/06-3/13/06.
Instead, I would like the start and finish date to reflect on the two days
that I could make this 30 minute call. I’ve looked through this forum,
glanced through Project 2003 For Dummies and I’ve done basic tutorials but
I’m still uncertain if the ‘window of time’ is doable. I hope this is clear.
Any help or advice would be greatly appreciated. Thanks in advance!
question. I am trying to track how long all of my tasks take, i.e. 30
minutes, not 1 day. Ultimately, I want to assign it to a week or a 2-day
window when I will do the task. What keeps happening is that I set the
duration for 30 minutes, but when I put a start and end date then it adds 2
days to my 30 minute task. Case in point, a task would be a 30-minute phone
call but I’m not sure when I can actually make the call but I know it will
happen somewhere on Tuesday or Wednesday. So the duration will and should be
30 minutes, BUT I don’t want the start and finish time to be 3/13/06-3/13/06.
Instead, I would like the start and finish date to reflect on the two days
that I could make this 30 minute call. I’ve looked through this forum,
glanced through Project 2003 For Dummies and I’ve done basic tutorials but
I’m still uncertain if the ‘window of time’ is doable. I hope this is clear.
Any help or advice would be greatly appreciated. Thanks in advance!