Hi DevourU,
many ways lead to Rome
so to speak, the same applies to managing
meetings. If you have regular status meetings you can incorporate them into
your schedule as recurring tasks, which generally works very well.
Should you require some "add hoc" meetings you may want to consider creating
an ad hoc meeting task bucket where you assign your resources to this task.
That will mean that every time they have a meeting they can update the task
using the my task functionality.
That would of course be different if you have to manage non project
meetings. I would not manage them in a project schedule but in the timesheet
directly by using admin tasks.
I hope this helps