S
Sebastián Armas
Greetings:
I'd like to know how to set-up Project Server so that only a Project Owner
would be able to update a gantt's % Complete and only through PWA.
Note that the idea is to NOT allow him to change the tasks' othe data, such
as resources involved, begin an end date, etc.
Thanks in advance for your kind reply,
Sebastián Armas
Software Engineer & Project Manager
I'd like to know how to set-up Project Server so that only a Project Owner
would be able to update a gantt's % Complete and only through PWA.
Note that the idea is to NOT allow him to change the tasks' othe data, such
as resources involved, begin an end date, etc.
Thanks in advance for your kind reply,
Sebastián Armas
Software Engineer & Project Manager