I am using:
- MS Project 2007
- Resource Pool
My resource pool has a custom field with values that get updated (PMO
maintained Project List) and validated in the Lookup Table for the custom
field (Text7)
I would like PMs to be able to update individual plans with the latest
values from the Resource Pool Text7 Lookup Table
Does anyone have a VBA script that deletes the Lookup Table list of the
Active project and copies in the values from the resource pool ?
Thanks,
- MarkP