L
luis.fls.marques
Hello everyone, I already posted this message in
microsoft.public.project.server but because this may require a custom
solution I am also posting it here
We are using MS Project Server 2007.
The big question is: How to Update Task Level Enterprise Custom Fields
in PWA?
The problem is that we have custom enterprise fields defined at task
level. What we would like to do is have resources assigned to tasks
update these task level fields. In our case, because we only have one
resource per task there wouldn’t be a problem with multiple resources
providing different updates.
As far as we can see, in PWA 2007, the only editable view that you can
provide updates is the Mytasks page. Mytasks allows us to display the
custom fields but when our team members update them, the custom fields
get updated at the assignment level but not at task level, so in
summary, there is no roll up of the updates... The consequence is that
when we open the project in project professional 2007 and go to the
Gantt chart view, the updates are not shown.
Is there any place in PWA (maybe using a different view) that allows
updating custom fields at task level rather than assignment level?
At this moment the only 2 alternatives I can see to achieve this is to
either write a server event handler that updates the task level custom
field when an update is done at assignment level or write a macro that
does this automatically whenever someone opens the project in MS
Project professional 2007 (easier to accomplish but maybe not as clean
as the server event handler option).
Has anyone come across this problem before?? and if so, what solution
did you implement?
Any help at this point would be greatly appreciated.
Regards,
Luis.
microsoft.public.project.server but because this may require a custom
solution I am also posting it here
We are using MS Project Server 2007.
The big question is: How to Update Task Level Enterprise Custom Fields
in PWA?
The problem is that we have custom enterprise fields defined at task
level. What we would like to do is have resources assigned to tasks
update these task level fields. In our case, because we only have one
resource per task there wouldn’t be a problem with multiple resources
providing different updates.
As far as we can see, in PWA 2007, the only editable view that you can
provide updates is the Mytasks page. Mytasks allows us to display the
custom fields but when our team members update them, the custom fields
get updated at the assignment level but not at task level, so in
summary, there is no roll up of the updates... The consequence is that
when we open the project in project professional 2007 and go to the
Gantt chart view, the updates are not shown.
Is there any place in PWA (maybe using a different view) that allows
updating custom fields at task level rather than assignment level?
At this moment the only 2 alternatives I can see to achieve this is to
either write a server event handler that updates the task level custom
field when an update is done at assignment level or write a macro that
does this automatically whenever someone opens the project in MS
Project professional 2007 (easier to accomplish but maybe not as clean
as the server event handler option).
Has anyone come across this problem before?? and if so, what solution
did you implement?
Any help at this point would be greatly appreciated.
Regards,
Luis.