I'm trying to figure out how to use the new Health field.

I've set the Health in My Tasks in PWA to Late...and submitted the
changes....and approved this update. When I open the mpp in Project 2007 and
insert the Health field, the change to Late doesn't show up...it shows "not
specified".

Next I changed the Health field in my mpp in Project 2007 and publish the
project....the changes to the Health field don't show up in my PWA tasklist.

How is this field supposed to work?
 
D

Dale Howard [MVP]

Jesse --

Unfortunately, I believe you are seeing one more bug in the Project Server
2007 system. You are not the only one who has reported that the Health
field does not seem to populate in the Microsoft Project plan. Hope this
helps.
 