S
Smugliy
Hi ,What is the best way to verify that there is no data in the future ? (for
example next 2 years)
When I am using TimeScaleData function ,start date is always "rounded" to
the start of the interval but I want it from next day(today +1) .If I will
use days interval I will need to iterate 365(days) * 2 = 730 times .And this
is only for one task .And I have much more taks.
May be there is an other way to do this ?
Thanks a lot.
example next 2 years)
When I am using TimeScaleData function ,start date is always "rounded" to
the start of the interval but I want it from next day(today +1) .If I will
use days interval I will need to iterate 365(days) * 2 = 730 times .And this
is only for one task .And I have much more taks.
May be there is an other way to do this ?
Thanks a lot.