J
jc
Good Morning:
Is there a way to show all assignments that are past the
finish date. For example, if Task1 is 80% complete and
the finish date is less than today's date how can I get
these tasks to show in a different color. Can this be
done automatically in MSProject 2000 or do I need to write
a Macro. If a macro is needed does anyone have an example?
Any help would be very much appreciated.
Thank you.
Is there a way to show all assignments that are past the
finish date. For example, if Task1 is 80% complete and
the finish date is less than today's date how can I get
these tasks to show in a different color. Can this be
done automatically in MSProject 2000 or do I need to write
a Macro. If a macro is needed does anyone have an example?
Any help would be very much appreciated.
Thank you.