We're been using Project 2003 for about 5 months. I created a view under
Assignments. I want to view planned cost and actual cost for all tasks for
all projects. I was able to put in the following fields for this view:
Project Name
Task name
Cost
Actual Cost
When I try to view it by going to Resources/View resource assignements, and
click on the view I created, all fields showed up, but no value showed under
the columns Cost and Actual Cost (even there're hours and costs associated
with the tasks shown).
Please show me how to show these cost and actual cost in this view.
Thanks,
Assignments. I want to view planned cost and actual cost for all tasks for
all projects. I was able to put in the following fields for this view:
Project Name
Task name
Cost
Actual Cost
When I try to view it by going to Resources/View resource assignements, and
click on the view I created, all fields showed up, but no value showed under
the columns Cost and Actual Cost (even there're hours and costs associated
with the tasks shown).
Please show me how to show these cost and actual cost in this view.
Thanks,