How to Weekly Scheduled Tasks

J

jaime

Hi,

How would I get a view of the tasks that need to be worked on for the
current week? And for the next week? Thanks

-jaime
 
J

Jan De Messemaeker

Hi,

The filter Date Range... will show these.
Project menu, Filtered For... select date range
Alternative: look for the filter in the filter window (you will see "All
Tasks")
HTH

--
Jan De Messemaeker
Microsoft Project Most Valuable Professional
+32 495 300 620
For availability check:
http://users.online.be/prom-ade/Calendar.pdf
 